|PublishedContracting Officer Final Decisions: FAR 33.211 Notice Rules
ByNational Compliance Registry Staff · Reviewer: NCR Editorial Team
Published · Updated

Requirements at a glance
| Requirement | Rule | Authority |
|---|---|---|
| Applicability | Applies to decisions on claims initiated by or against the contractor. Contractor claims against the Federal Government must be submitted in writing to the contracting officer. | FAR 33.211(a)-(b); 41 U.S.C. § 7103(a) |
| Decision timing | For claims of $100,000 or less, a decision is due within 60 days after a qualifying written request, or within a reasonable time without that request. For claims over $100,000, the 60-day period follows receipt of a certified claim; if a decision will take longer, the contractor must be notified within that period. | FAR 33.211(c)-(d); 41 U.S.C. § 7103(f) |
| Delivery method | Furnish the decision by Certified Mail, return receipt requested, or another method that provides evidence of receipt. | FAR 33.211(b); 41 U.S.C. § 7103(d) |
| Board appeal | A contractor may appeal to an agency board within 90 days from the date of receipt. The notice identifies the decision and contract and is provided to the board, with a copy to the contracting officer. | FAR 33.211(a)(4)(v); 41 U.S.C. § 7104(a) |
| Court action | In lieu of a board appeal, a contractor may bring an action in the U.S. Court of Federal Claims within 12 months from receipt. The statute provides an exception for certain Maritime Contracts and a separate venue rule for Tennessee Valley Authority actions. | FAR 33.211(a)(4)(v); 41 U.S.C. § 7104(b) |
| Exceptions and alternate procedures | A timely written defective-certification notice can relieve the contracting officer of the obligation to issue a decision on a claim over $100,000. Failure to decide within required time periods is deemed a denial. Board procedures include the regulation’s small-claim thresholds of $50,000 or less, or $150,000 or less for a qualifying small business, and an accelerated threshold of $100,000 or less. | FAR 33.211(e), (g), (a)(4)(v); 41 U.S.C. § 7103(b)(3), (f)(5) |
FAR 33.211 requires a contracting officer to furnish a final decision by Certified Mail, return receipt requested, or another method that provides evidence of receipt. For a contractor appealing a decision, the date of receipt starts the 90-day agency board appeal period and the 12-month Court of Federal Claims filing period. The retained receipt record documents the date used to calculate those deadlines.
Decision content and timing
A contracting officer prepares a written decision when a claim cannot be settled by agreement and a decision is necessary. The decision describes the claim, identifies relevant contract terms, states areas of factual agreement and disagreement, and explains the determination. It also includes notice paragraphs substantially matching FAR 33.211(a)(4)(v). If the decision finds the contractor indebted to the Government, it includes a payment demand prepared under FAR 32.604 and 32.605.
For claims over $100,000, the contractor’s certification states that the claim is made in good faith, supporting data are accurate and complete to the best of the contractor’s knowledge and belief, the amount accurately reflects the requested contract adjustment, and the certifier is authorized to act for the contractor. A defect does not deprive a court or agency board of jurisdiction. The tribunal must require correction before final judgment or decision.
A written notice of a defective certification within 60 days of receiving the claim is a separate process. When the claim exceeds $100,000 and the notice explains the defect, FAR 33.211(e) states that the contracting officer has no obligation to render a final decision on that claim. This notice should not be confused with a final decision or an appeal notice.
Receipt evidence and appeal clocks
The delivery rule concerns proof of receipt, not simply dispatch. A mailing record can show when an item was sent. A return receipt or another reliable delivery record can help establish when the contractor received the decision. The received date is the statutory reference point for the appeal periods.
The 90-day board period and 12-month court period are alternative routes stated in the decision notice and 41 U.S.C. 7104. The board notice must indicate an intent to appeal, reference the decision, identify the contract by number, and be furnished to the board with a copy to the contracting officer. A Court of Federal Claims action proceeds de novo under the statute. Applicable contract circumstances and the specific tribunal route require careful review.
The requirements for Certified Mail and proof-of-mailing records distinguish mailing evidence from evidence that the recipient received a notice. For the return receipt record, review paper and electronic proof-of-delivery options. A consistent notice file can also follow the audit trail framework for legal notices.

Practical implementation guidance
Keep legal requirements distinct from internal controls. FAR 33.211 establishes the decision content, delivery method, and certain timing rules. The following steps organize the records needed to verify those requirements and manage the deadlines.
- Validate the decision package. Confirm the decision identifies the claim, relevant contract terms, factual agreements and disagreements, rationale, and appeal-rights notice. Confirm a payment demand is included when required.
- Select and document delivery. Use Certified Mail with return receipt requested or another method that produces evidence of receipt. Record the method, destination, dispatch date, tracking or reference number, and the person or system responsible for monitoring delivery.
- Capture the receipt date. Save the completed return receipt or other delivery evidence, including available recipient and date details. Record the receipt date in the claim file and deadline tracker. Keep proof of mailing separate from proof of receipt; see how proof of mailing differs from proof of notice.
- Calendar both statutory routes. Calculate the 90-day board period and 12-month court filing period from the documented receipt date. Identify the chosen path and assign a responsible owner for deadline monitoring. Do not treat an internal calendar entry as a substitute for the underlying delivery evidence.
- Track claim-processing events separately. Record written requests for decisions, certified-claim receipt dates, extension notices, and any defective-certification notice. These records support review of the decision timetable and related actions.
For related contract-notice subjects, use the Government Contracting notices hub as the main topic reference.
Evidence-file checklist
Retain an organized file that supports both the decision content and the delivery chronology.
- Contractor claim, supporting submissions, and any written request for a decision.
- Certification for a claim over $100,000 and related correspondence.
- Contracting officer’s written decision and attachments.
- Review materials documenting contract terms, factual issues, rationale, and required payment demand, where applicable.
- Copy of the appeal-rights notice included with the decision.
- Delivery method, destination, dispatch date, tracking or transaction reference, and mailing documentation.
- Return receipt or other record showing delivery and the date of receipt.
- Deadline calculation identifying the receipt date, board deadline, court deadline, and responsible owner.
- Any written defective-certification notice and evidence of its date and delivery.
- Any notice of a decision extension, tribunal request, or deemed-denial event.

Deemed denial and delayed decisions
FAR 33.211(g) treats a contracting officer’s failure to issue a decision within the required time periods as a decision denying the claim. That deemed denial authorizes the contractor to file an appeal or suit. The statute also allows the tribunal, at its option, to stay proceedings to obtain a contracting officer decision. When delay is undue, FAR 33.211(f) permits the contractor to ask the tribunal to direct issuance within a specified period.
A deemed denial is distinct from a delivered final decision. It arises from failure to decide within the applicable time, not from proof of receipt of a written decision. Preserve the claim submission date, certification record where applicable, written decision requests, notices, and correspondence used to assess the decision period. The amount determined payable under a decision, less amounts already paid, should be paid if otherwise proper without awaiting contractor appeal action; that payment is without prejudice to either party’s rights.
Frequently asked questions
What delivery methods satisfy FAR 33.211(b)?
The contracting officer must use Certified Mail, return receipt requested, or another method that provides evidence of receipt. Retain records that establish both the delivery method and the receipt date. Source: FAR 33.211, Contracting officer’s decision
When does the 90-day board appeal period begin?
It runs from the date the contractor receives the contracting officer’s decision. The delivery record supports calculation of that date. Source: 41 U.S.C. § 7103, Decision by contracting officer
What is the deadline for a Court of Federal Claims action?
A contractor may bring an action in lieu of a board appeal within 12 months from receipt of the decision. The statute provides exceptions and separate rules for specified circumstances. Source: 41 U.S.C. § 7104, Contractor’s right of appeal from decision by contracting officer
Does a defective certification eliminate tribunal jurisdiction?
No. A defect in certification does not deprive a court or agency board of jurisdiction. The tribunal must require correction before entering a final judgment or decision. A timely written defect notice can separately remove the contracting officer’s obligation to decide a claim over $100,000. Source: 41 U.S.C. § 7104, Contractor’s right of appeal from decision by contracting officer
What happens if the contracting officer does not issue a decision on time?
The failure is deemed a denial and authorizes an appeal or suit. The file should document the claim’s receipt, any qualifying decision request or certification, and correspondence relevant to the decision period. Source: 41 U.S.C. § 7104, Contractor’s right of appeal from decision by contracting officer
Sources
About the author and review
Author: National Compliance Registry Staff.
Reviewer: NCR Editorial Team.
National Compliance Registry editorial staff maintain these research guides; no individual credential is claimed. Read our editorial methodology and corrections process.
Related resources
Update history
First published November 24, 2026. No material revisions are documented in the article record.
This article provides general compliance information, not legal advice.